Project Finance Term Sheet: The Complete Institutional Guide

Last Updated: November 2026

Quick Summary

A project finance term sheet defines economics (margin, fees, tenor), structure (debt sizing, amortisation, security), and risk allocation (covenants, CPs, events of default). Sponsors typically have 15–25 negotiable points: margin step-downs, cash sweep thresholds, distribution lock-up tests, reserve account sizing, and permitted indebtedness baskets are where economic value is captured or lost.

Pairs with our Project Financing Guide and Deal Structuring reference.

What a Project Finance Term Sheet Actually Does

A term sheet is the binding (or partially binding) commercial blueprint that lenders and sponsors agree before drafting facility agreements. It typically runs 25–60 pages in institutional project finance and locks in the economics that govern the next 7–25 years. Misjudging a single clause — for example accepting a 1.20x distribution lock-up rather than 1.15x — can trap hundreds of millions of dollars of equity returns inside the project company.

Section 1: Economics and Pricing

  • Margin: 175–350 bps over SOFR/EURIBOR for investment-grade renewables; 350–650 bps for greenfield emerging-market infrastructure.
  • Margin Ratchet: Step-downs of 25–50 bps tied to leverage or DSCR milestones. Always negotiate symmetric step-ups, not just one-way step-downs.
  • Upfront Fee: 1.00%–2.50% of facility size, paid at financial close.
  • Commitment Fee: 35–50% of margin on undrawn amounts during construction.
  • Agency & Security Trustee Fees: $75k–$250k p.a. depending on syndicate size.
  • Hedging Costs: Mandatory interest rate hedge for 75–100% of debt over 80%+ of tenor.

Section 2: Structure and Sizing

Debt is sized off the lower of two tests: a leverage cap (typically 70–80% of project cost) and a coverage-based sizing (debt service that produces a minimum 1.30x DSCR under base case and 1.10x under sponsor downside). Tenor for renewables sits at PPA tenor minus 2–3 years tail; mining and oil & gas typically cap at 7–10 years post-completion.

  • Amortisation: Sculpted (target DSCR) for contracted cash flows; mortgage-style for merchant.
  • Cash Sweep: 50–100% of excess cash flow above target DSCR until leverage falls below trigger.
  • Balloon: Avoid >25% balloons; refinancing risk is heavily penalised in rating reviews.

Section 3: Security Package

  • Share pledge over the project company (100%)
  • Account pledges over all project accounts including DSRA and MMRA
  • Assignment of project documents (EPC, O&M, offtake, insurance)
  • Mortgage/charge over the project site and all moveable assets
  • Step-in rights via direct agreements with each material counterparty
  • Sponsor support: equity contribution undertakings, cost overrun facilities, completion guarantees

Section 4: Covenants — The High-Stakes Section

Financial Covenants

  • Historic DSCR: Tested every 6 months on trailing 12 months, typically >1.10x.
  • Forecast DSCR: Forward-looking 12-month test, typically >1.15x.
  • Distribution Lock-up DSCR: Both historic and forecast must exceed 1.20–1.25x before equity distributions.
  • LLCR: >1.40x at every test date.

Information & Operational Covenants

  • Quarterly compliance certificates with model re-run
  • Annual lender base case update and budget approval
  • Restrictions on permitted indebtedness, permitted disposals, and material contract amendments
  • Insurance covenants tied to lender-approved insurance advisor reports

Section 5: Conditions Precedent (CPs)

Financial close is gated by 60–120 CPs. The most commonly missed are: legal opinions in every relevant jurisdiction, tax rulings, regulatory consents (especially environmental and grid connection), KYC on every shareholder up the chain, and execution of all direct agreements. Build a CP tracker on day one of negotiations — every CP added on the lender side compounds delay risk.

Section 6: Reserve Accounts

  • Debt Service Reserve Account (DSRA): 6 months of forward debt service, cash- or LC-funded.
  • Maintenance Reserve Account (MRA): Funded against rolling 24-month forward maintenance schedule.
  • Decommissioning Reserve: Required for renewables and mining; funded over project life.

Section 7: Events of Default

Standard EoDs include payment default (2–5 day grace), covenant breach, cross-default at $5–10M threshold, change of control without lender consent, abandonment, and material adverse change. Negotiate MAC tightly — broad MAC clauses give lenders unilateral repricing leverage.

Sponsor Negotiation Playbook

  1. Run a competitive process. Two-bank shortlist minimum; three is optimal. Comparing term sheets side-by-side typically yields 15–35 bps margin compression.
  2. Push for symmetric ratchets and a leverage-based step-down.
  3. Negotiate distribution lock-up at 1.15x, not 1.20x — this single point can unlock $20–40M of early equity distributions on a $200M facility.
  4. Cap MAC clauses to objective, measurable triggers.
  5. Build flexibility into permitted indebtedness, permitted acquisitions, and refinancing rights.
  6. Front-load CP work. Use a dedicated CP coordinator from week one.

Term sheet checklist

Before signing, confirm the term sheet covers:

  • Facility amount, tranches, tenor and repayment profile
  • Margin, fees, hedging requirements and interest rate basis
  • Debt sizing: target DSCR, gearing cap and sculpting
  • Security package and intercreditor arrangements
  • Financial covenants, distribution lock-up and default ratios
  • Reserve accounts (debt service, maintenance)
  • Conditions precedent and timetable to financial close
  • Which clauses are binding: exclusivity, costs, confidentiality, governing law

Lofotr Investors does not review or negotiate term sheets; use your lawyers and, for larger facilities, a financial adviser. We screen projects raising $2M to $5B+ and introduce suitable ones to capital providers. Start a project funding enquiry.

Get Term Sheet-Ready Capital Introductions

We screen projects and introduce suitable ones to institutional debt and equity providers. No upfront fee; funding is not guaranteed.

Start a Project Funding Enquiry

Frequently Asked Questions

Most term sheets are partially binding: confidentiality, exclusivity, costs, and governing law clauses are binding; commercial terms are usually subject to credit committee approval and final documentation.

Typically 4–9 months for greenfield project finance, depending on jurisdiction complexity, environmental permitting, and number of CPs. Brownfield refinancings can close in 8–12 weeks.

The distribution lock-up DSCR. A move from 1.20x to 1.15x can release tens of millions of equity returns earlier in the project life. Margin ratchet symmetry and MAC scoping rank close behind.

Base case DSCR of 1.30x is typical for contracted renewable and infrastructure assets; 1.40–1.60x for merchant or commodity-exposed projects. Distribution lock-ups sit 5–10 bps tighter.

For facilities above $50M, yes. The fee (typically 0.5–1.0% of debt raised) is repaid many times over through margin compression, covenant flexibility, and fewer CPs.