What is Bankability?
Bankability is a project's inherent ability to satisfy the risk tolerance of commercial lenders. It represents the threshold at which a mining project becomes eligible for senior debt financing—the largest and cheapest source of development capital. As the single most comprehensive resource on mining funding explains, achieving bankability is the critical gateway to large-scale capital.
PEA vs PFS vs DFS (BFS) at a Glance
| Study | Typical cost accuracy | Resource basis | Can support senior debt? |
|---|---|---|---|
| Scoping study / PEA | About ±30–50% | Can include Inferred Resources | No |
| Pre-feasibility study (PFS) | About ±20–25% | Measured and Indicated; first Reserves | Rarely; may support streams, royalties or strategic equity |
| Definitive / bankable feasibility study (DFS or BFS) | About ±10–15% | Proven and Probable Reserves | Yes, once reviewed by the lenders' independent engineer |
"DFS" and "BFS" usually mean the same thing. "Bankable" is not a formal standard: a study is bankable only when the lenders and their independent engineer accept it as a basis for lending. A DFS typically costs a few per cent of the project's capital cost and takes about one to two years.
The Feasibility Study Hierarchy
Lenders rely on a progressive hierarchy of engineering studies to assess technical and economic viability:
Preliminary Economic Assessment (PEA)
- Accuracy: about ±30–50% on capital and operating costs
- Bankability Status: NOT Bankable
- Purpose: Initial "go/no-go" decision for further investment
- Resource Basis: Can use Inferred Resources
- Use: Attracting early equity investors, strategic partners
Pre-Feasibility Study (PFS)
- Accuracy: about ±20–25% on capital and operating costs
- Bankability Status: Semi-Bankable (may attract alternative finance)
- Purpose: Confirm project viability, define optimal development plan
- Resource Basis: Indicated Resources (minimum)
- Use: Securing streaming/royalty capital, strategic equity
Definitive Feasibility Study (DFS) / Bankable Feasibility Study (BFS)
- Accuracy: about ±10–15% on capital and operating costs
- Bankability Status: MANDATORY for senior debt
- Purpose: Final investment decision, basis for project financing
- Resource Basis: Proven and Probable Reserves (minimum)
- Use: Securing project finance, construction debt
Resources vs. Reserves: The Critical Distinction
Lenders require Reserves, not Resources, to support mine life projections:
| Category | Confidence Level | Bankable? |
|---|---|---|
| Inferred Resource | Low (geological extrapolation) | No |
| Indicated Resource | Moderate (reasonable confidence) | Partially (supports PFS) |
| Measured Resource | High (detailed sampling) | Partially (supports conversion) |
| Probable Reserve | Economically viable (from Indicated) | Yes |
| Proven Reserve | Economically viable (from Measured) | Yes |
The Independent Engineer
Lenders require an Independent Engineer (IE) to verify the DFS and monitor project execution:
- Role: Technical advisor to the lending syndicate
- Scope: Review DFS, validate assumptions, monitor construction
- Common Firms: SRK, Hatch, Wood, Stantec, SLR
- Deliverables: Independent Technical Report confirming bankability
Financial Modeling Requirements
The financial model is the quantitative foundation of bankability. It must be robust, transparent, and auditable.
Debt Service Coverage Ratio (DSCR)
DSCR measures the project's ability to service debt obligations from operating cash flow:
DSCR = Cash Available for Debt Service / Total Debt Service
- Minimum Requirement: 1.30x (typical), 1.50x (conservative)
- Interpretation: DSCR of 1.30x means 30% buffer above debt payments
- Calculation Period: Each period during debt repayment
Loan Life Coverage Ratio (LLCR)
LLCR measures the project's ability to repay debt over the entire loan life:
LLCR = NPV of Cash Flow / Outstanding Debt
- Minimum Requirement: 1.40x (typical), 1.60x (conservative)
- Interpretation: LLCR of 1.40x means 40% present value buffer
- Discount Rate: Typically the loan interest rate
Sensitivity Analysis
Models must stress-test against adverse scenarios:
- Commodity Price: -20% to -30% from base case
- CAPEX Overrun: +15% to +25%
- OPEX Increase: +10% to +20%
- Production Delay: 6-12 months
- Recovery Rate: -5% to -10%
- Currency Fluctuation: ±15% on local costs
Legal and Contracting Certainty
Bankability requires comprehensive legal documentation:
Essential Documentation
- Mining License: Valid, transferable, with adequate tenure
- Environmental Permits: All required approvals in place
- Social License to Operate: Community agreements, resettlement plans
- Host Government Agreement: Fiscal stabilization, arbitration clauses
- EPC Contract: Fixed-price or guaranteed maximum price preferred
- Offtake Agreements: Take-or-pay commitments from creditworthy buyers
- Power Purchase Agreement: Secured energy supply
- Water Rights: Confirmed water access for operations
EPC Contract Considerations
- Fixed Price: Contractor assumes cost overrun risk
- Liquidated Damages: Penalties for delays or performance shortfalls
- Performance Guarantees: Contractor guarantees plant output
- Retention: Funds held until performance proven
- Parent Company Guarantee: Contractor's parent backs obligations
The Bankability Checklist
- ✓ Definitive Feasibility Study (±10% accuracy)
- ✓ Proven and Probable Reserves (JORC/NI 43-101 compliant)
- ✓ Independent Engineer validation
- ✓ DSCR ≥ 1.30x throughout loan life
- ✓ LLCR ≥ 1.40x
- ✓ All permits and licenses secured
- ✓ Binding offtake agreements
- ✓ EPC contract with performance guarantees
- ✓ Experienced management team
- ✓ Acceptable ESG performance
- ✓ Political risk mitigation (HGA, insurance)
Continue Your Learning
Return to the single most comprehensive resource on mining funding for the complete financing picture.